What was once an eyesore and was finally cleaned up and landscaped will now become a construction zone as Phase 2 of the Expo Light Rail Line begins.
Work crews will remove existing train tracks along the Expo right-of-way in Rancho Park and Cheviot Hills starting January 9. The work should be completed in April, according to BuildExpo.org.
Work crews will remove the existing railroad tracks consisting of rails, fasteners, and ties from Military Avenue to Bagley Avenue.
Heavy machinery and flat bed trucks with back-up alarms will be utilized for this work. Flaggers will be used to assist trucks hauling debris as they enter and exit work areas on Military Avenue, Westwood Boulevard, Overland Avenue, Motor Avenue, National Boulevard, and Bagley Avenue.
Access to businesses and residences will be maintained. Noise levels will be monitored. Work crews will water down the work area to minimize dust, and the air will be monitored.
Report problems and make suggestions: Glenda Y. Silva Exposition Construction Authority Tel. 213-243-5534 gsilva@exporail.net
Hotline: 213-922-EXPO
Skanska-Rados Joint Venture will be removing the track: 310-220-9329 Jim.Kennedy2@Skanska.com
Want the latest news about Rancho Park, join now!
––––––––––––––––––––––––––––––
Membership has its privileges!
• Got news you think everyone should know? Blog it.
• Have a show or attending a benefit? Put it on the calendar.
• Got video of the big game? Embed it.
• Photos of the new storefront or the school play? Upload them.
© 2024 Created by Rancho Park Online. Powered by
You need to be a member of Rancho Park Online to add comments!
Join Rancho Park Online